Order To Cash (IF) (OTC-IF) Tower
Capability LO-180
IAO Program
Generated: May 2026
Sajiv Francis
Companion to LO-180-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| LO-180 | Manage Outbound Transportation - OTC (IF) | 13/13 | 114/114 | 48% | 80% | 100% | — | 🟡 AMBER |
LO-180 Totals: 13/13 L3 in-scope · 12/25 config complete · 65/81 Fit · 37/37 RICEFW complete · 0/0 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 25 |
| Config CDD Complete | 12 |
| Average Completion | 48% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
| LO-180 | Manage Outbound… | 81 | 65 | 16 | 80% | — |
LO-180: 65/81 Fit-to-Standard (80%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| LO-180 | Manage Outbound… | 37 | 37 | 0 | — |
LO-180: 37/37 complete (100%)
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | LO-180 | Config Incomplete | Config at 48% (12/25) | 🟡 MEDIUM |
Summary: 🔴 0 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
LO-180 — Process Readiness Detail · Order To Cash (IF) · Generated: May 2026