PLB-020 — Supply Planning & Management (IF)

RICEFW Object Tracker

Forecast to Stock — Intel Foundry (FTS-IF) Tower
Capability PLB-020 · PLB Supply Chain Planning (IF)

IAO Program · R1 – R5
Generated: May 2026
Sajiv Francis

IAO Architecture Pipeline — Intel Confidential

Table of Contents

1. Executive Summary

This tracker provides the development object inventory and build progress for Forecast to Stock — Intel Foundry (FTS-IF) — PLB-020 Supply Planning & Management (IF).

Metric Value
Total Dev Objects 7
S/4 RICEFW Objects 7
Active (In Progress) 2
Completed 5
Rejected / Cancelled 0
S/4 RICEFW Breakdown 4 Interfaces, 3 Enhancements
Avg FS Completion 100%
Avg Build Completion 86%
Avg FUT Completion 71%

2. Dev Object Inventory

2.1 Summary by Type

Type Code Count % of Total
Interface I 4 57%
Enhancement E 3 43%
Total 7 100%

2.2 Summary by Status

Status Count % of Total
Completed 5 71%
06. Dev In Progress 2 29%

3. S/4 RICEFW Objects

3.1 Interfaces

Active (2):

Object ID Description Status Source → Target Middleware Complexity Build %
FTSI1021 Interface to be developed from ECA to SAP which helps to upload PIR via BAPI 06. Dev In Progress ECA → S/4 APIGEE 03.Medium 1.0
FTSI0860 Interface to create Kanban trigger from DMRA and get Reservation created and … 06. Dev In Progress DMRA → S/4 MULESOFT 01.Very High 0.0
Completed (2):
Object ID Description Source → Target Middleware Complexity
FTSI1157 Custom program for STO generation for Raw Silicon 3PL → S/4 APIGEE 03.Medium
FTSI1020 IMO - Interface from NBS to S4 to induct stock from IMO plant to S4 NBS → S/4 APIGEE 03.Medium
### 3.2 Conversions

No conversion objects for this capability.

3.3 Enhancements

Completed (3):

Object ID Description Source → Target Middleware Complexity
FTSE1160 Custom Utility for Engineering Planners to create Rev Eng Planned Orders in S4 NA 03.Medium
FTSE1019 WIINGS factory portal UI to send signal for raw material consumption in S4 NA 02.High
FTSE0506 Custom table to store planned orders and pegged sales orders in S4 NA 03.Medium
### 3.4 Reports

No report objects for this capability.

3.5 Forms

No form objects for this capability.

3.6 Workflows

No workflow objects for this capability.

4. Build Progress

4.1 Phase Completion

Object ID Description FS TDD Build FUT Status
FTSI1021 Interface to be developed from ECA to… 2025-03-21 00:00:00 (100%) 2025-05-02 00:00:00 (100%) 2025-05-02 00:00:00 (100%) 5. Not Dispositioned
FTSI0860 Interface to create Kanban trigger fr… 2025-03-21 00:00:00 (100%) 5. Not Dispositioned

4.2 Delivery Timeline

Phase On Track Off Track Not Started Avg Completion
Functional Spec 2 0 0 100%
Technical Design 1 0 1 50%
Build & TUT 1 0 1 50%
FUT 0 0 2 0%

5. Risk Items

RAID items will be populated from the Master RAID Log.

6. Change Requests

194 approved change requests impact this capability.

CR ID Title Priority Release Category Completion New Objs Descoped
INT-CR0014 Additional Logistics L2/L3 to be included in R2… High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0020 Plant Maintenance effort for SWAP (WIINGS) High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0021 Spares - Quality Management High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0024 Foundry Quality and Reliability (FQR) team: R3 … High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0040 R3 Stakeholder Assessment Medium R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0043 Change in technical approach of MPL Waybill fro… High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0066 Material Master-VERP Materials Manual Conversion Very High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0074 Match Trade Flows to Physical Flows Very High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0083 Initial ECA Code/TUT Planned End Date’, ‘ECA Co… High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0087 Transportation Management L3’s Reopen High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0164 Addition of L3s in Exception Topic for Design S… High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0201 Reopen L3s for Gases/Chemicals R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0207 Correct L3 to be added under exception topic Oe… High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0216 Integration from PDH to S4 to capture yield and… Medium R3 (Feb 2027) Complete 2.0 0.0
INT-CR0224 SAP Role Build to Align to Tower based Apps/Tra… Medium R1 (May 2025) Complete 0.0 0.0
INT-CR0250 IF R3 - OTC RICEFW for Order Confirmation (usin… High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0337 Descope these objects : FTSI0411,FTSI0254,FTSI0… Medium R3 (Feb 2027) In Progress 0.0 11.0
INT-CR0350 Cancellation of RICEFW Object: LOGI1151 (Duplic… Medium R3 (Feb 2027) In Progress 0.0 1.0
INT-CR0379 Descope these objects : FTSI0268_IF Medium R3 (Feb 2027) In Progress 0.0 1.0
INT-CR0383 ECA -Lot Projection TPT Report High R2 (Aug 2025) In Progress 0.0 0.0
Showing top 20 of 194 change requests.

Generated by IAO Architecture Pipeline · May 2026 · Intel Confidential