Forecast to Stock (IF) (FTS-IF) Tower
Capability M-090
IAO Program
Generated: May 2026
Sajiv Francis
Companion to M-090-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| M-090 | Schedule Production (IF) | 15/15 | 165/165 | 52% | — | 71% | — | 🟡 AMBER |
M-090 Totals: 15/15 L3 in-scope · 15/29 config complete · 0/0 Fit · 5/7 RICEFW complete · 0/0 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 29 |
| Config CDD Complete | 15 |
| Average Completion | 52% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
M-090: 0/0 Fit-to-Standard (0%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| M-090 | Schedule Production (IF) | 7 | 5 | 2 | — |
M-090: 5/7 complete (71%)
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | M-090 | RICEFW Incomplete | 2/7 objects not complete | 🟡 MEDIUM |
Summary: 🔴 0 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
M-090 — Process Readiness Detail · Forecast to Stock (IF) · Generated: May 2026