Forecast to Stock — Intel Products (FTS-IP) Tower
Capability M-080 · M Mfg. Schedule and Execution (IP)
IAO Program · R1 – R5
Generated: April 2026
Sajiv Francis
IAO Architecture Pipeline — Intel Confidential
This report provides the testing and quality status for Forecast to Stock — Intel Products (FTS-IP) — M-080 Perform Materials Requirement Planning (IP) sourced from JIRA (cached April 2026).
| Metric | Value |
|---|---|
| Total RICEFW Objects | 101 |
| Objects with Test Coverage | 99 (98%) |
| Test Cases | 0 |
| Pass Rate | 0% |
| Open Defects | 0 |
| Critical Defects | 0 |
| FUT Avg Completion | 98% |
| Build Avg Completion | 86% |
| RICEFW Type | Total Objects | FUT Started | FUT % Avg | Build % Avg |
|---|---|---|---|---|
| Interface | 34 | 33 | 97% | 100% |
| Conversion | 20 | 20 | 100% | 35% |
| Enhancement | 35 | 34 | 97% | 97% |
| Report | 2 | 2 | 100% | 100% |
| Form | 7 | 7 | 100% | 100% |
| Workflow | 3 | 3 | 100% | 100% |
| Total | 101 | 99 | 98% | 86% |
| Status | Count | % |
|---|---|---|
| Passed | 0 | 0% |
| Failed | 0 | 0% |
| Blocked | 0 | 0% |
| Not Run | 0 | 0% |
| Total | 0 | 100% |
| Object ID | Type | Description | FUT % | FUT Status | Build % |
|---|---|---|---|---|---|
| LOGE1327 | E | ECD_Enhancement to retrieve plant det… | 90% | In Progress | 100% |
| LOGE0935_IP | E | Fiori App - Shipping Memo | 92% | In Progress | 100% |
| FTSI1693 | I | Interface for Reporting Scrap of Semi… | 100% | Complete | 100% |
| LOGI1584 | I | Interface to post inventory in SAP S/… | — | Not Started | 100% |
| FTSE1739 | E | Develop Utility for mass change of Pr… | — | Not Started | — |
| Test Scenario | Status | Related RICEFW | Defects |
|---|---|---|---|
| Test Scenario | Status | Sign-off | Business Owner |
|---|---|---|---|
| Severity | Open | In Progress | Resolved | Total |
|---|---|---|---|---|
| Total | 0 | 0 | 0 | 0 |
| Age Bucket | Critical | High | Medium | Low |
|---|---|---|---|---|
| Defect ID | Severity | Summary | Status | Assignee | Days Open |
|---|---|---|---|---|---|
| Sprint | Start | End | Committed | Completed | Velocity |
|---|---|---|---|---|---|
| Criterion | Status | Evidence |
|---|---|---|
| All critical defects resolved | ✅ Pass | JIRA defect query |
| Test pass rate ≥ 95% | ⚠️ 0% | JIRA test execution |
| UAT sign-off obtained | ⏳ Pending | JIRA UAT board |
| No P0/P1 blockers open | ✅ Clear | JIRA issue tracker |
Generated by IAO Architecture Pipeline · April 2026 · Intel Confidential