🏭 M-090 — Schedule Production (IF)

M Mfg. Schedule and Execution (IF)

📄 Systems Architecture Document 📋 RICEFW Tracker 🧪 Testing Report

RICEFW Objects (7.8 FTS IF - MRP & Planning Integration)

📋 7 objects ✅ 5 complete (71%) ⏳ 2 pending
Object IDTypeDescriptionStatusAssessment
FTSE050604.EnhancementCustom table to store planned orders and pegged sales orders in S410. Object Complete
FTSE101904.EnhancementWIINGS factory portal UI to send signal for raw material consumption in S410. Object Complete
FTSE116004.EnhancementCustom Utility for Engineering Planners to create Rev Eng Planned Orders in S410. Object Complete
FTSI086002.InterfaceInterface to create Kanban trigger from DMRA and get Reservation created and ...06. Dev In Progress
FTSI102002.InterfaceIMO - Interface from NBS to S4 to induct stock from IMO plant to S410. Object Complete
FTSI102102.InterfaceInterface to be developed from ECA to SAP which helps to upload PIR via BAPI06. Dev In Progress
FTSI115702.InterfaceCustom program for STO generation for Raw Silicon10. Object Complete

Defects (JIRA)

🐛 6 total 🔴 1 critical 6 resolved