Order To Cash (IP) (OTC-IP) Tower
Capability O-060
IAO Program
Generated: May 2026
Sajiv Francis
Companion to O-060-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| O-060 | Manage and Track Orders (IP) | 4/4 | 56/56 | 12% | 37% | 99% | 93% | 🔴 RED |
O-060 Totals: 4/4 L3 in-scope · 2/17 config complete · 10/27 Fit · 81/82 RICEFW complete · 13/14 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 17 |
| Config CDD Complete | 2 |
| Average Completion | 12% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
| O-060 | Manage and Track Orders (IP) | 27 | 10 | 14 | 37% | — |
O-060: 10/27 Fit-to-Standard (37%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| O-060 | Manage and Track Orders (IP) | 82 | 81 | 1 | — |
O-060: 81/82 complete (99%)
ECA (Enterprise Cloud Analytics) object completion by L2 capability — Reports, Views, Ingestion, and 3rd Party objects tracked in the ECA R3 Object Tracker.
| L2 Code | Description | Active | Complete | In Progress | ECA % | Rejected |
|---|---|---|---|---|---|---|
| O-060 | Manage and Track Orders (IP) | 14 | 13 | 1 | 93% | 23 |
O-060: 13/14 ECA complete (93%)
Data Source: ECA [R3] IDM Object Tracker (Smartsheet). Rejected/cancelled objects excluded from active counts. Objects mapped via Sub-Tower Name → L2 capability.
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | O-060 | Config Incomplete | Config at 12% (2/17) | 🔴 HIGH |
| 2 | O-060 | Low Fit-to-Standard | Only 37% Fit (10/27) | 🟡 MEDIUM |
Summary: 🔴 1 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
O-060 — Process Readiness Detail · Order To Cash (IP) · Generated: May 2026