Order To Cash (IF) (OTC-IF) Tower
Capability CM-060
IAO Program
Generated: May 2026
Sajiv Francis
Companion to CM-060-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| CM-060 | Manage Collections (IF) | 33/33 | 133/133 | 31% | 94% | 100% | — | 🟡 AMBER |
CM-060 Totals: 33/33 L3 in-scope · 10/32 config complete · 29/31 Fit · 9/9 RICEFW complete · 0/0 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 32 |
| Config CDD Complete | 10 |
| Average Completion | 31% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
| CM-060 | Manage Collections (IF) | 31 | 29 | 2 | 94% | — |
CM-060: 29/31 Fit-to-Standard (94%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| CM-060 | Manage Collections (IF) | 9 | 9 | 0 | — |
CM-060: 9/9 complete (100%)
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | CM-060 | Config Incomplete | Config at 31% (10/32) | 🟡 MEDIUM |
Summary: 🔴 0 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
CM-060 — Process Readiness Detail · Order To Cash (IF) · Generated: May 2026