Forecast to Stock (IP) (FTS-IP) Tower
Capability PLB-020
IAO Program
Generated: May 2026
Sajiv Francis
Companion to PLB-020-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| PLB-020 | Supply Planning & Management (IP) | 3/3 | 28/28 | 55% | — | 100% | — | 🟢 GREEN |
PLB-020 Totals: 3/3 L3 in-scope · 6/11 config complete · 0/0 Fit · 5/5 RICEFW complete · 0/0 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 11 |
| Config CDD Complete | 6 |
| Average Completion | 55% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
PLB-020: 0/0 Fit-to-Standard (0%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| PLB-020 | Supply Planning & Management (IP) | 5 | 5 | 0 | — |
PLB-020: 5/5 complete (100%)
All automated risk flags detected across data sources.
✅ No risk flags detected for PLB-020.
← Back to Architecture Document
PLB-020 — Process Readiness Detail · Forecast to Stock (IP) · Generated: May 2026