Forecast to Stock (IP) (FTS-IP) Tower
Capability M-100
IAO Program
Generated: May 2026
Sajiv Francis
Companion to M-100-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| M-100 | Execute Production (IP) | 8/8 | 211/211 | 0% | — | 88% | — | 🔴 RED |
M-100 Totals: 8/8 L3 in-scope · 0/12 config complete · 0/0 Fit · 14/16 RICEFW complete · 0/0 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 12 |
| Config CDD Complete | 0 |
| Average Completion | 0% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
M-100: 0/0 Fit-to-Standard (0%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| M-100 | Execute Production (IP) | 16 | 14 | 2 | — |
M-100: 14/16 complete (88%)
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | M-100 | Config Incomplete | Config at 0% (0/12) | 🔴 HIGH |
| 2 | M-100 | RICEFW Incomplete | 2/16 objects not complete | 🟡 MEDIUM |
Summary: 🔴 1 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
M-100 — Process Readiness Detail · Forecast to Stock (IP) · Generated: May 2026