M-080 — Perform Materials Requirement Planning (IP)

RICEFW Object Tracker

Forecast to Stock — Intel Products (FTS-IP) Tower
Capability M-080 · M Mfg. Schedule and Execution (IP)

IAO Program · R1 – R5
Generated: May 2026
Sajiv Francis

IAO Architecture Pipeline — Intel Confidential

Table of Contents

1. Executive Summary

This tracker provides the development object inventory and build progress for Forecast to Stock — Intel Products (FTS-IP) — M-080 Perform Materials Requirement Planning (IP).

Metric Value
Total Dev Objects 5
S/4 RICEFW Objects 5
Active (In Progress) 0
Completed 5
Rejected / Cancelled 0
S/4 RICEFW Breakdown 2 Interfaces, 3 Enhancements

2. Dev Object Inventory

2.1 Summary by Type

Type Code Count % of Total
Interface I 2 40%
Enhancement E 3 60%
Total 5 100%

2.2 Summary by Status

Status Count % of Total
Completed 5 100%

3. S/4 RICEFW Objects

3.1 Interfaces

Completed (2):

Object ID Description Source → Target Middleware Complexity
FTSI0210 Interface Function to Create Purchase Requisitions from ECA to S/4 ECA (PDH) → S/4 BODS 03.Medium
FTSI0209 Interface to create Production Order from ECA to S/4 ECA (PDH) → S/4 BODS 03.Medium
### 3.2 Conversions

No conversion objects for this capability.

3.3 Enhancements

Completed (3):

Object ID Description Source → Target Middleware Complexity
FTSE1694 Enhancement to Introduction of additional restrictions by MRP Area for S4 IP … NA 03.Medium
FTSE1597 Develop a utility for mass creation of production orders via load file in SAP… NA 02.High
FTSE1146 Enhancement to link KB sales orders / STR to purchase requisition generated b… NA 04.Low
### 3.4 Reports

No report objects for this capability.

3.5 Forms

No form objects for this capability.

3.6 Workflows

No workflow objects for this capability.

4. Build Progress

4.1 Phase Completion

Timeline data will be populated from Smartsheet Object Tracker.

4.2 Delivery Timeline

Phase statistics will be populated from Smartsheet Object Tracker.

5. Risk Items

RAID items will be populated from the Master RAID Log.

6. Change Requests

125 approved change requests impact this capability.

CR ID Title Priority Release Category Completion New Objs Descoped
INT-CR0040 R3 Stakeholder Assessment Medium R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0087 Transportation Management L3’s Reopen High R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0168 IP to IF Turn-key Order Process High R3 (Feb 2027) Complete 0.0 0.0
INT-CR0216 Integration from PDH to S4 to capture yield and… Medium R3 (Feb 2027) Complete 2.0 0.0
INT-CR0224 SAP Role Build to Align to Tower based Apps/Tra… Medium R1 (May 2025) Complete 0.0 0.0
INT-CR0259 Publish scenario design in BY High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0260 IP Gaplog Intake Process & MVP Tool High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0285 OSAT 7B1 integration for IP using SMH High R3 (Feb 2027) Design / Build Gap In Progress 0.0 0.0
INT-CR0303 Cancel Objects: LOGI0336, LOGI0518, LOGI0519_IP… Medium R3 (Feb 2027) In Progress 0.0 5.0
INT-CR0304 Cancel Objects: FTSI0560 - SAP IBP to SAP S4 - … Medium R3 (Feb 2027) In Progress 0.0 1.0
INT-CR0314 New requirement change in the business process … Medium R3 (Feb 2027) Complete 0.0 0.0
INT-CR0348 Cancellation of RICEFW Objects: 1.FTSI0834_IF (… Medium R3 (Feb 2027) In Progress 0.0 2.0
INT-CR0402 Master Data Configuration for ISM Fiori App Design Medium R3 (Feb 2027) Complete 0.0 0.0
INT-CR0460 Cancellation of RICEFW Objects: FTSE1141 (we di… Medium R3 (Feb 2027) In Progress 0.0 1.0
INT-CR0474 Build Ahead Limits Medium R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0479 Descope Data Privacy - Intel Privacy Office has… Very High R1 (May 2025) Complete 0.0 0.0
INT-CR0512 Forecast Reprofiling Very High R2 (Aug 2025) In Progress 0.0 0.0
INT-CR0526 Cancellation of RICEFW Objects: FTSE1145 - Enha… Medium R3 (Feb 2027) In Progress 0.0 1.0
INT-CR0539 Cancel object ID PTPE0473_IF Demand Change - Au… Medium R3 (Feb 2027) In Progress 0.0 0.0
INT-CR0581 Adjust WIINGS milestones to match IAO Replan R3 (Feb 2027) In Progress 0.0 0.0
Showing top 20 of 125 change requests.