Finance Plan To Report (FPR) Tower
Capability OR-140
IAO Program
Generated: May 2026
Sajiv Francis
Companion to OR-140-Architecture.html — IAO Architecture Pipeline — Intel Confidential
← Back to Architecture Document
| L2 Code | Description | L3 (scope/total) | L4 (scope/total) | Config % | Fit-to-Std % | RICEFW % | ECA % | Status |
|---|---|---|---|---|---|---|---|---|
| OR-140 | Process Receipts | 13/13 | 57/57 | 33% | 63% | 100% | 39% | 🔴 RED |
OR-140 Totals: 13/13 L3 in-scope · 5/15 config complete · 105/167 Fit · 24/24 RICEFW complete · 22/56 ECA complete
Per-L2 configuration tracker detail showing CDD completion against required items.
| Metric | Value |
|---|---|
| Config Items Required | 15 |
| Config CDD Complete | 5 |
| Average Completion | 33% |
Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.
| L2 Code | Description | Total | Fit | Gap | Fit % | Gaps w/o RICEFW |
|---|---|---|---|---|---|---|
| OR-140 | Process Receipts | 167 | 105 | 62 | 63% | — |
OR-140: 105/167 Fit-to-Standard (63%)
Development object completion by L2 capability.
| L2 Code | Description | Total | Complete | In Progress | Not Started |
|---|---|---|---|---|---|
| OR-140 | Process Receipts | 24 | 24 | 0 | — |
OR-140: 24/24 complete (100%)
ECA (Enterprise Cloud Analytics) object completion by L2 capability — Reports, Views, Ingestion, and 3rd Party objects tracked in the ECA R3 Object Tracker.
| L2 Code | Description | Active | Complete | In Progress | ECA % | Rejected |
|---|---|---|---|---|---|---|
| OR-140 | Process Receipts | 56 | 22 | 34 | 39% | 41 |
OR-140: 22/56 ECA complete (39%)
Data Source: ECA [R3] IDM Object Tracker (Smartsheet). Rejected/cancelled objects excluded from active counts. Objects mapped via Sub-Tower Name → L2 capability.
All automated risk flags detected across data sources.
| # | L2 | Flag | Detail | Severity |
|---|---|---|---|---|
| 1 | OR-140 | Config Incomplete | Config at 33% (5/15) | 🟡 MEDIUM |
| 2 | OR-140 | ECA Incomplete | 34/56 ECA objects not complete (39%) | 🔴 HIGH |
Summary: 🔴 1 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW
← Back to Architecture Document
OR-140 — Process Readiness Detail · Finance Plan To Report · Generated: May 2026