Table of Contents

  1. Capability Readiness Summary
  2. Configuration Status
  3. User Story Coverage
  4. RICEFW Object Status
  5. Risk Flag Register

1. Capability Readiness Summary

L2 Code Description L3 (scope/total) L4 (scope/total) Config % Fit-to-Std % RICEFW % ECA % Status
DC-100 Revenue Recognition 5/6 81/88 86% 72% 100% 🟢 GREEN

DC-100 Totals: 5/6 L3 in-scope · 6/7 config complete · 28/39 Fit · 14/14 RICEFW complete · 0/0 ECA complete

2. Configuration Status

Per-L2 configuration tracker detail showing CDD completion against required items.

DC-100 — Revenue Recognition

Metric Value
Config Items Required 7
Config CDD Complete 6
Average Completion 86%

3. User Story Coverage

Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.

L2 Code Description Total Fit Gap Fit % Gaps w/o RICEFW
DC-100 Revenue Recognition 39 28 10 72%

DC-100: 28/39 Fit-to-Standard (72%)

4. RICEFW Object Status

Development object completion by L2 capability.

L2 Code Description Total Complete In Progress Not Started
DC-100 Revenue Recognition 14 14 0

DC-100: 14/14 complete (100%)

7. Risk Flag Register

All automated risk flags detected across data sources.

✅ No risk flags detected for DC-100.