1. Executive Summary

This report provides the testing and quality status for Finance Plan to Report (FPR) — DC-050 Project Accounting sourced from JIRA (cached May 2026).

Metric Value
Total RICEFW Objects 367
Objects with Test Coverage 363 (99%)
Test Cases 0
Pass Rate 0%
Open Defects 15
Critical Defects 1
FUT Avg Completion 98%
Build Avg Completion 98%

2. Test Coverage

2.1 Coverage by RICEFW Type

RICEFW Type Total Objects FUT Started FUT % Avg Build % Avg
Interface 86 86 100% 100%
Conversion 25 25 96% 87%
Enhancement 220 216 97% 99%
Report 17 17 100% 100%
Form 1 1 100% 100%
Workflow 18 18 100% 100%
Total 367 363 98% 98%

2.2 Test Case Summary

Status Count %
Passed 0 0%
Failed 0 0%
Blocked 0 0%
Not Run 0 0%
Total 0 100%

3. Test Execution Status

3.1 Functional Unit Testing (FUT)

Object ID Type Description FUT % FUT Status Build %
FPRE1661_IF E WBS transfer tool 95% In Progress 100%
FPRE1599_IP E Update existing custom table ZTFPR_AC… 55% In Progress 100%
FPRE1599_IF E Update existing custom table ZTFPR_AC… 55% In Progress 100%
FPRE0880 E Cash concentration functionality for … 50% In Progress 100%
FPRC1724_IP C Creation of output template with cons… 55% In Progress 92%
FPRC1724_IF C Creation of output template with cons… 55% In Progress 92%
FPRE1741 E Mobile timesheet approval for Intel F… Not Started

3.2 Integration Testing

Test Scenario Status Related RICEFW Defects

3.3 User Acceptance Testing (UAT)

Test Scenario Status Sign-off Business Owner

4. Defect Analysis

4.1 Defects by Severity

Severity Open In Progress Resolved Total
Critical 1 0 0 1
High 7 1 29 37
Medium 6 0 20 26
Total 15 1 49 64

4.2 Defect Aging

Age Bucket Critical High Medium Low
0–7 days 0 1 3 0
8–14 days 1 1 0 0
15–30 days 0 3 1 0
31–60 days 0 3 2 0
60+ days 0 0 0 0

4.3 Open Defects

Showing 15 open/in-progress defects. 365 resolved defects are in the Resolved Defects Log.

Defect ID Severity Summary Status Assignee Days Open
IAODTM-9336 Critical FPRXV071 - I cannot see any values in the “Open… To Do Nawal, RavichandX Ugamchand 11
IAODTM-8609 High FPRXV072- JV DETAILS report Blocked Joshi, KetanX Jeevanrao 34
IAODTM-8632 High ECA Aging AUC Raw Data - Project Hierarchy Fiel… To Do Chauhan, AnkushX 33
IAODTM-8662 High FPRXV215: CW Report, legacy data vs ECA data an… In Analysis Andrico, Liesl 32
IAODTM-8719 High FPRXV230: Sample Report not available To Do Morgan, Kara L 28
IAODTM-8749 High FPRXV0170 - Project Deactivation issue (Project… In Progress Kumar, AmitX 26
IAODTM-9014 High View not assigned for the fields in for report … To Do Sharma, PragathiX 18
IAODTM-9387 High FPRXV0110 - Lineage file is not well defined. To Do Breton, ArturoX Galindo 11
IAODTM-9598 High FPRXV075 - 21 WBS elements listed in BI REPORT … To Do Elizondo Mora, Gabriel 7
IAODTM-8380 Medium ECAFPR6090 FPRXV212 - Consolidated Spending and… In Analysis Avula, SureshX 47
IAODTM-8429 Medium ECAFPR6064 FPRXV170 Project Deactivation (OpEx)… To Do Bustamante, Paul A 45
IAODTM-9054 Medium Comments added in the Excel for the lineage FPR… In Analysis Nawal, RavichandX Ugamchand 17
IAODTM-9672 Medium Project Status HANA report — FPRXV172 In Analysis Nawal, RavichandX Ugamchand 6
IAODTM-9797 Medium FPRC0174 - WBS Elements with ? in extract files To Do Nawal, RavichandX Ugamchand 4
IAODTM-9790 Medium FPRC0174 - Missing Expense Projects in Extract … To Do Nawal, RavichandX Ugamchand 4

5. Sprint Status

Sprint Start End Committed Completed Velocity

6. Go-Live Readiness

Criterion Status Evidence
All critical defects resolved ❌ 1 open JIRA defect query
Test pass rate ≥ 95% ⚠️ 0% JIRA test execution
UAT sign-off obtained ❌ 1 critical blockers JIRA UAT board
No P0/P1 blockers open ❌ 1 blockers JIRA issue tracker