Finance Plan to Report (FPR) Tower
Capability DC-050 · DC Manage Accounting and Control Data
IAO Program · R1 – R5
Generated: May 2026
Sajiv Francis
IAO Architecture Pipeline — Intel Confidential
This tracker provides the development object inventory and build progress for Finance Plan to Report (FPR) — DC-050 Project Accounting.
| Metric | Value |
|---|---|
| Total Dev Objects | 186 |
| S/4 RICEFW Objects | 87 |
| ECA Objects | 99 |
| Active (In Progress) | 26 |
| Completed | 113 |
| Rejected / Cancelled | 47 |
| S/4 RICEFW Breakdown | 9 Interfaces, 12 Conversions, 52 Enhancements, 4 Reports, 10 Workflows |
| ECA Breakdown | 40 ECA Views, 32 3rd Party Reports, 22 ECA Ingestions, 5 ECA Self-Service Datas |
| Avg FS Completion | 88% |
| Avg Build Completion | 75% |
| Avg FUT Completion | 63% |
| Type | Code | Count | % of Total |
|---|---|---|---|
| Interface | I | 9 | 5% |
| Conversion | C | 12 | 6% |
| Enhancement | E | 52 | 28% |
| Report | R | 4 | 2% |
| Workflow | W | 10 | 5% |
| ECA View | EV | 40 | 22% |
| 3rd Party Report | 3P | 32 | 17% |
| ECA Ingestion | EI | 22 | 12% |
| ECA Self-Service Data | ES | 5 | 3% |
| Total | 186 | 100% |
| Status | Count | % of Total |
|---|---|---|
| Completed | 113 | 61% |
| Rejected / Cancelled | 47 | 25% |
| 07. FUT Not Started | 19 | 10% |
| 09. FUT Overdue | 3 | 2% |
| 03. FS Not Started | 2 | 1% |
| 01. Pending Approval | 1 | 1% |
| 02. FS Unplanned | 1 | 1% |
Completed (9):
| Object ID | Description | Source → Target | Middleware | Complexity |
|---|---|---|---|---|
| FPRI1670 | Import Dot process/stage details from MDG into S4. | NA | 03.Medium | |
| FPRI1669 | Import Xeus/Mars volumes from ECA into S4. | BODS | 03.Medium | |
| FPRI1463 | Interface to upload payroll data from Workday to S/4 IP for legal entity 199 … | MULESOFT | 03.Medium | |
| FPRI1238 | Pull Foundry WBS from HAT and create in LE 199 in IP S/4 for Foundry Employee… | Head Count Assignment Tool → S/4 | BODS | 03.Medium |
| FPRI0981_IP | Interface of SAP PPM module to SPEED | ECA → S/4 | BODS | 03.Medium |
| FPRI0981_IF | Interface of SAP PPM module to SPEED | ECA → S/4 | BODS | 04.Low |
| FPRI0909_IP | Interface for importing the Headcount details by Person# and WBS element comb… | ECA → S/4 | BODS | 03.Medium |
| FPRI0909_IF | Interface for importing the Headcount details by Person# and WBS element comb… | ECA → S/4 | BODS | 04.Low |
| FPRI0188 | Inbound Interface from EMS to S/4 to create WBS element and Update WBS elemen… | XEUS → S/4 | APIGEE | 02.High |
| ### 3.2 Conversions |
Completed (12):
| Object ID | Description | Source → Target | Middleware | Complexity |
|---|---|---|---|---|
| FPRC1565 | Convert active delegate relationships for Timesheet approval | NA | 02.High | |
| FPRC1464_IP | Project Actuals Conversion (Non- Intel Federal) | NA | 02.High | |
| FPRC1464_IF | Project Actuals Conversion (Non- Intel Federal) | NA | 02.High | |
| FPRC1442 | Conversion of Actual Labor hours for Intel Federal Projects | NA | 02.High | |
| FPRC1441 | Conversion of ECC project hierarchy (WBS element master data) to S/4HANA proj… | NA | 02.High | |
| FPRC1212 | Project Actuals Conversion including Intel Federal | NA | 03.Medium | |
| FPRC0908_IP | Project Budget Conversion | NA | 03.Medium | |
| FPRC0908_IF | Project Budget Conversion | NA | 03.Medium | |
| FPRC0174_IP | Conversion of ECC project hierarchy (WBS element master data) to S/4HANA proj… | ECC → S4 | NA | 02.High |
| FPRC0174_IF | Conversion of ECC project hierarchy (WBS element master data) to S/4HANA proj… | ECC → S4 | NA | 03.Medium |
| FPRC0035_IP | Convert existing ECC & MDG hierarchy to S4HANA PPM hierarchy (Portfolio & buc… | → MDG | NA | 03.Medium |
| FPRC0035_IF | Convert existing ECC & MDG hierarchy to S4HANA PPM hierarchy (Portfolio & buc… | → MDG | NA | 04.Low |
| ### 3.3 Enhancements |
Active (2):
| Object ID | Description | Status | Source → Target | Middleware | Complexity | Build % |
|---|---|---|---|---|---|---|
| FPRE1661_IF | WBS transfer tool | 09. FUT Overdue | NA | 03.Medium | 1.0 | |
| FPRE1741 | Mobile timesheet approval for Intel Federal employees. | 01. Pending Approval | NA | 01.Very High | 0.0 | |
| Completed (49): |
| Object ID | Description | Source → Target | Middleware | Complexity |
|---|---|---|---|---|
| FPRE1695 | Custom Fiori app - Change WBS Element Request Form with ALV Input | NA | 03.Medium | |
| FPRE1671_IP | S4, Perform required calculations, summarizations, mappings and post the allo… | NA | 03.Medium | |
| FPRE1671_IF | S4, Perform required calculations, summarizations, mappings and post the allo… | NA | 04.Low | |
| FPRE1661_IP | WBS transfer tool | NA | 02.High | |
| FPRE1600 | Custom Fiori app - Create WBS Element Request Form with ALV Input | NA | 03.Medium | |
| FPRE1564 | Employee Notification for timesheet entry | NA | 03.Medium | |
| FPRE1563 | Manager notification for timesheet approval | NA | 03.Medium | |
| FPRE1562 | Manage Delegates for approval | NA | 03.Medium | |
| FPRE1561 | Timesheet approval | NA | 02.High | |
| FPRE1560 | Timesheet entry for Intel Federal employees | NA | 01.Very High | |
| FPRE1553 | Custom Fiori app - Change WBS Element Request Form with ALV Input | NA | 03.Medium | |
| FPRE1519_IP | Project Change Order - Edit and Submit of draft request with change functiona… | NA | 02.High | |
| FPRE1519_IF | Project Change Order - Edit and Submit of draft request with change functiona… | NA | 03.Medium | |
| FPRE1518_IP | Project Change Order - Change existing Purchase Orders during creation of Pro… | NA | 02.High | |
| FPRE1518_IF | Project Change Order - Change existing Purchase Orders during creation of Pro… | NA | 03.Medium | |
| FPRE1517_IP | Project Change Order - Create Purchase Orders during creation of Project Chan… | NA | 02.High | |
| FPRE1517_IF | Project Change Order - Create Purchase Orders during creation of Project Chan… | NA | 03.Medium | |
| FPRE1516_IP | Enhancement to enable user decision action to be taken from email directly fo… | NA | 03.Medium | |
| FPRE1516_IF | Enhancement to enable user decision action to be taken from email directly fo… | NA | 04.Low | |
| FPRE1515_IP | Enhancement to display popup screen to trigger project creation workflow | NA | 03.Medium | |
| FPRE1515_IF | Enhancement to display popup screen to trigger project creation workflow | NA | 04.Low | |
| FPRE1235_IP | Add custom fields to CJI3 and CJI5 reports (SAP S/4HANA Project Systems modul… | NA | 03.Medium | |
| FPRE1235_IF | Add custom fields to CJI3 and CJI5 reports (SAP S/4HANA Project Systems modul… | NA | 04.Low | |
| FPRE1209 | Upload adjustments to time sheet entries in bulk for Intel Federal. | NA | 02.High | |
| FPRE1104_IP | WBS with custom attributes will be created in the PS module. The master data … | NA | 02.High | |
| FPRE1104_IF | WBS with custom attributes will be created in the PS module. The master data … | NA | 03.Medium | |
| FPRE1025_IP | Custom Fiori app will be created using Free style model to display WBS/AUC re… | NA | 03.Medium | |
| FPRE1025_IF | Custom Fiori app will be created using Free style model to display WBS/AUC re… | NA | 04.Low | |
| FPRE0942_IP | Interface of SAP PPM module to ATLAS | S4 → ATLAS | NA | 03.Medium |
| FPRE0942_IF | Interface of SAP PPM module to ATLAS | S4 → ATLAS | NA | 04.Low |
| FPRE0890_IP | Investment type creation and automatic settlement rule generation for Opex Pr… | NA | 03.Medium | |
| FPRE0890_IF | Investment type creation and automatic settlement rule generation for Opex Pr… | NA | 04.Low | |
| FPRE0888_IP | Mass Update Fields in WBS Elements | NA | 02.High | |
| FPRE0888_IF | Mass Update Fields in WBS Elements | NA | 03.Medium | |
| FPRE0887_IP | WBS Element field synchronization to AUC and Fixed assets - Construction ID -… | NA | 03.Medium | |
| FPRE0887_IF | WBS Element field synchronization to AUC and Fixed assets - Construction ID -… | NA | 04.Low | |
| FPRE0886_IP | Project Change Order - Create Project Change Order via custom Fiori Screens w… | NA | 02.High | |
| FPRE0886_IF | Project Change Order - Create Project Change Order via custom Fiori Screens w… | NA | 03.Medium | |
| FPRE0885 | Custom Fiori app - Create WBS Element Request Form with ALV Input | NA | 03.Medium | |
| FPRE0884_IP | Custom Fiori app - CPA (Project Budget) approval request using PPM Item decis… | NA | 02.High | |
| FPRE0884_IF | Custom Fiori app - CPA (Project Budget) approval request using PPM Item decis… | NA | 03.Medium | |
| FPRE0877_IP | Automation to set TECO and CLSD status on Project/ WBS | NA | 02.High | |
| FPRE0877_IF | Automation to set TECO and CLSD status on Project/ WBS | NA | 03.Medium | |
| FPRE0495_IP | Custom Fields in WBS element Master Data | NA | 03.Medium | |
| FPRE0495_IF | Custom Fields in WBS element Master Data | NA | 04.Low | |
| FPRE0315_IP | Activation of custom enhancement tab on portfolio bucket for custom fields. | NA → NA | NA | 03.Medium |
| FPRE0315_IF | Activation of custom enhancement tab on portfolio bucket for custom fields. | NA → NA | NA | 04.Low |
| FPRE0314_IP | Smart numbering for portfolio items. | NA → NA | NA | 03.Medium |
| FPRE0314_IF | Smart numbering for portfolio items. | NA → NA | NA | 04.Low |
| ### 3.4 Reports |
Completed (4):
| Object ID | Description | Source → Target | Middleware | Complexity |
|---|---|---|---|---|
| FPRR1211 | Report for searching on and viewing government contract timesheets for Intel … | NA | 03.Medium | |
| FPRR1210 | Report for searching on and viewing government contract timesheet changes for… | NA | 03.Medium | |
| FPRR0907_IP | Workflow Status Report ( Order Request / Approval Request / Others ) | NA | 03.Medium | |
| FPRR0907_IF | Workflow Status Report ( Order Request / Approval Request / Others ) | NA | 04.Low | |
| ### 3.5 Forms |
No form objects for this capability.
Completed (10):
| Object ID | Description | Source → Target | Middleware | Complexity |
|---|---|---|---|---|
| FPRW1064_IP | Custom Workflow will also be created with some predefined process/rules for a… | NA | 01.Very High | |
| FPRW1064_IF | Custom Workflow will also be created with some predefined process/rules for a… | NA | 02.High | |
| FPRW0906_IP | Custom workflow: Change Order Create and Change Approval | NA | 03.Medium | |
| FPRW0906_IF | Custom workflow: Change Order Create and Change Approval | NA | 03.Medium | |
| FPRW0904_IP | Custom Workflow - WBS Element Request approval with WBS Element creation | NA | 03.Medium | |
| FPRW0904_IF | Custom Workflow - WBS Element Request approval with WBS Element creation | NA | 03.Medium | |
| FPRW0900_IP | Custom Workflow: Approval for Project creation and create a Project def and l… | NA | 03.Medium | |
| FPRW0900_IF | Custom Workflow: Approval for Project creation and create a Project def and l… | NA | 03.Medium | |
| FPRW0445_IP | Project budget approval workflow (Capex) | NA | 03.Medium | |
| FPRW0445_IF | Project budget approval workflow (Capex) | NA | 03.Medium |
Completed (21):
| Object ID | Description | Sub-Tower | Complexity |
|---|---|---|---|
| FPRXV409 | WBS Element Structure | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV411 | Portfolio Bucket Item Detail | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV412 | Asset Master | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV413 | Change Order Process | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV414 | Portfolio Financial Group Budget | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV445 | Portfolio Financial Group Plan | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV446 | Settlement Rule Header Line | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV447 | AUC Asset Master | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV473 | Wbs Element Project Detail | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV474 | Overdue Depreciation Accrual | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV475 | Asset Time Dependent | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV531 | Project Spend Detail | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV532 | Actuals Commit PO Detail | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV533 | WBS Depreciation Term Tmtrvl | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV551 | Budget Plan Document Header Line | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV552 | Budget Plan Total Value | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV553 | WBS Depreciation Term | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV556 | Plan Open Commitment Value Line | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV557 | Asset Depreciation Term | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV559 | Project Budget Actuals | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV560 | Change Order Approver | 3.11 FPR - Project Accounting | 03.Medium |
| ### 4.2 3rd Party Reports |
Active (24):
| Object ID | Description | Status | Sub-Tower | Complexity | FS % | TDD % | Build % | FUT % |
|---|---|---|---|---|---|---|---|---|
| FPRXV070 | Budget Overview | 07. FUT Not Started | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV071 | Open PO Report | 09. FUT Overdue | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.75 |
| FPRXV072 | Run JV Detail Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV073 | Capital Spends Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV074 | Capital Commits Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV075 | Large Construction, Commits and Spends (CPM | 07. FUT Not Started | 3.11 FPR - Project Accounting | 02.High | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV079 | Budget Commit Actual Details | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV110 | WBS DSD Change History | 07. FUT Not Started | 3.11 FPR - Project Accounting | 1.0 | 1.0 | 1.0 | 0.0 | |
| FPRXV131 | Priority List for Construction | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV172 | Project Status HANA report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV174 | Large Construction CPM Approvals | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV175 | Large Construction CPM Change Order Log | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV176 | Large Construction, CPM SOV | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV177 | Large Construction ECO-PCO Log | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV210 | Combining PCOS Spending and OpEx Reporting - from Node or Stage perspective | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV211 | Lifetime forecast rollup by Business unit, functional area and project master… | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV215 | CW Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV216 | FTM Close Summary Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV217 | Non-PO Report | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV224 | LTRCA Report | 03. FS Not Started | 3.11 FPR - Project Accounting | 03.Medium | 0.0 | 0.0 | 0.0 | 0.0 |
| FPRXV229 | Resource Grid | 09. FUT Overdue | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.75 |
| FPRXV230 | Project Actuals vs Forecast CapEx | 07. FUT Not Started | 3.11 FPR - Project Accounting | 03.Medium | 1.0 | 1.0 | 1.0 | 0.0 |
| FPRXV232 | Pre vs. Post Reorg Report | 03. FS Not Started | 3.11 FPR - Project Accounting | 03.Medium | 0.0 | 0.0 | 0.0 | 0.0 |
| FPRXR136 | Guardband Checkbook | 02. FS Unplanned | 3.11 FPR - Project Accounting | 03.Medium | 0.0 | 0.0 | 0.0 | 0.0 |
| Completed (8): |
| Object ID | Description | Sub-Tower | Complexity |
|---|---|---|---|
| FPRXV003 | Portfolio / Bucket Hierarchy View | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV121 | WBS Element Overview | 3.11 FPR - Project Accounting | |
| FPRXV122 | WBS Element Long Text | 3.11 FPR - Project Accounting | |
| FPRXV169 | Headcount Assignment Report (OpEx) | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV170 | Project Deactivation (OpEx) | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV209 | Post-allocated spending | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV212 | Consolidated Spending and Headcount Report | 3.11 FPR - Project Accounting | 03.Medium |
| FPRXV214 | Project Management Report | 3.11 FPR - Project Accounting | 03.Medium |
| Object ID | Description | FS | TDD | Build | FUT | Status |
|---|---|---|---|---|---|---|
| FPRE1661_IF | WBS transfer tool | 2026-01-07 00:00:00 (100%) | 2026-02-04 00:00:00 (100%) | 2026-02-04 00:00:00 (100%) | 2026-03-20 00:00:00 (95%) | 3. Off Track |
| FPRXV070 | Budget Overview | Nov-24 (100%) | — | — | — | |
| FPRXV071 | Open PO Report | Nov-24 (100%) | — | — | Apr-26 (75%) | |
| FPRXV072 | Run JV Detail Report | Nov-24 (100%) | — | — | — | |
| FPRXV073 | Capital Spends Report | Nov-24 (100%) | — | — | — | 3. Off Track |
| FPRXV074 | Capital Commits Report | Feb-25 (100%) | — | — | — | 3. Off Track |
| FPRXV075 | Large Construction, Commits and Spend… | Nov-24 (100%) | — | — | — | |
| FPRXV079 | Budget Commit Actual Details | Feb-25 (100%) | — | — | — | 3. Off Track |
| FPRXV110 | WBS DSD Change History | Feb-25 (100%) | — | — | — | |
| FPRXV131 | Priority List for Construction | Apr-25 (100%) | — | — | — | |
| FPRXV172 | Project Status HANA report | Jan-25 (100%) | — | — | — | |
| FPRXV174 | Large Construction CPM Approvals | Apr-25 (100%) | — | — | — | |
| FPRXV175 | Large Construction CPM Change Order Log | Apr-25 (100%) | — | — | — | |
| FPRXV176 | Large Construction, CPM SOV | Apr-25 (100%) | — | — | — | |
| FPRXV177 | Large Construction ECO-PCO Log | Jan-25 (100%) | — | — | — | |
| FPRXV210 | Combining PCOS Spending and OpEx Repo… | Apr-25 (100%) | — | — | — | |
| FPRXV211 | Lifetime forecast rollup by Business … | Apr-25 (100%) | — | — | — | 1. On Track |
| FPRXV215 | CW Report | Apr-25 (100%) | — | — | — | 1. On Track |
| FPRXV216 | FTM Close Summary Report | May-25 (100%) | — | — | — | |
| FPRXV217 | Non-PO Report | May-25 (100%) | — | — | — | |
| FPRXV229 | Resource Grid | May-25 (100%) | — | — | Apr-26 (75%) | |
| FPRXV230 | Project Actuals vs Forecast CapEx | May-25 (100%) | — | — | — |
| Phase | On Track | Off Track | Not Started | Avg Completion |
|---|---|---|---|---|
| Functional Spec | 22 | 0 | 4 | 85% |
| Technical Design | 22 | 0 | 4 | 85% |
| Build & TUT | 22 | 0 | 4 | 85% |
| FUT | 2 | 1 | 23 | 9% |
RAID items will be populated from the Master RAID Log.
335 approved change requests impact this capability.
| CR ID | Title | Priority | Release | Category | Completion | New Objs | Descoped |
|---|---|---|---|---|---|---|---|
| INT-CR0013 | Change in Treasury Scope | High | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0016 | Blackline vs CFIN JE Tool | High | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0020 | Plant Maintenance effort for SWAP (WIINGS) | High | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0032 | Intercompany Transfer Pricing - PaPM | High | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0035 | Release Change for Treasury Interface FPRI0168 … | Medium | R1 (May 2025) | In Progress | 0.0 | 2.0 | |
| INT-CR0036 | Recon Reports for Automated Data Conversion Obj… | High | R1 (May 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0037 | Near Real Time Reporting on HANA SideCar for FPR | Very High | R1 (May 2025) | In Progress | 0.0 | 0.0 | |
| INT-CR0038 | ECA/Analytics Recon Reports for Automated Data … | High | R1 (May 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0040 | R3 Stakeholder Assessment | Medium | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0041 | Improve Criteria for Extracting Cost Center Hie… | Medium | R1 (May 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0042 | ECA Recon Reports for Cost Center & Profit Cent… | High | R1 (May 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0044 | SAP Stock Room Management (SRM) for Returns War… | Very High | R3 (Feb 2027) | In Progress | 0.0 | 0.0 | |
| INT-CR0050 | IAO - eHana ( Sidecar Hana) reports - Security | High | R2 (Aug 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0051 | Company code move to difference S4 instance 776… | High | R3 (Feb 2027) | Complete | 0.0 | 0.0 | |
| INT-CR0059 | Split Load ready files in BODS & Improve extrac… | Medium | R1 (May 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0060 | Inclusion of logic for Batch Split scenario in … | Medium | R2 (Aug 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0061 | Commercial Invoice / KTBL Changes | High | R2 (Aug 2025) | Complete | 0.0 | 0.0 | |
| INT-CR0062 | WRICEF object for Exchange Rates M,R,S,I - S4 c… | Medium | R1 (May 2025) | In Progress | 0.0 | 0.0 | |
| INT-CR0068 | UIPath - Payment Remittance Advise | High | R3 (Feb 2027) | Complete | 10.0 | 0.0 | |
| INT-CR0069 | Debit Credit Memo Report with approval status -… | Medium | R2 (Aug 2025) | Complete | 0.0 | 0.0 | |
| Showing top 20 of 335 change requests. |
Generated by IAO Architecture Pipeline · May 2026 · Intel Confidential