DC-030 — Process Readiness Detail

Perform Closing

Finance Plan To Report (FPR) Tower
Capability DC-030

IAO Program
Generated: May 2026
Sajiv Francis

Companion to DC-030-Architecture.html — IAO Architecture Pipeline — Intel Confidential


Back to Architecture Document


Table of Contents

  1. Capability Readiness Summary
  2. Configuration Status
  3. User Story Coverage
  4. RICEFW Object Status
  5. Risk Flag Register

1. Capability Readiness Summary

L2 Code Description L3 (scope/total) L4 (scope/total) Config % Fit-to-Std % RICEFW % ECA % Status
DC-030 Perform Closing 96/96 654/654 17% 64% 95% 67% 🔴 RED

DC-030 Totals: 96/96 L3 in-scope · 6/35 config complete · 423/659 Fit · 77/81 RICEFW complete · 20/30 ECA complete

2. Configuration Status

Per-L2 configuration tracker detail showing CDD completion against required items.

DC-030 — Perform Closing

Metric Value
Config Items Required 35
Config CDD Complete 6
Average Completion 17%

3. User Story Coverage

Fit/Gap analysis from the User Story Tracker, grouped by L2 capability.

L2 Code Description Total Fit Gap Fit % Gaps w/o RICEFW
DC-030 Perform Closing 659 423 132 64%

DC-030: 423/659 Fit-to-Standard (64%)

4. RICEFW Object Status

Development object completion by L2 capability.

L2 Code Description Total Complete In Progress Not Started
DC-030 Perform Closing 81 77 4

DC-030: 77/81 complete (95%)

4b. ECA Object Status

ECA (Enterprise Cloud Analytics) object completion by L2 capability — Reports, Views, Ingestion, and 3rd Party objects tracked in the ECA R3 Object Tracker.

L2 Code Description Active Complete In Progress ECA % Rejected
DC-030 Perform Closing 30 20 10 67% 3

DC-030: 20/30 ECA complete (67%)

Data Source: ECA [R3] IDM Object Tracker (Smartsheet). Rejected/cancelled objects excluded from active counts. Objects mapped via Sub-Tower Name → L2 capability.

7. Risk Flag Register

All automated risk flags detected across data sources.

# L2 Flag Detail Severity
1 DC-030 Config Incomplete Config at 17% (6/35) 🔴 HIGH
2 DC-030 ECA Incomplete 10/30 ECA objects not complete (67%) 🟡 MEDIUM

Summary: 🔴 1 HIGH · 🟡 1 MEDIUM · 🔵 0 LOW